Pembroke Resources | C019 Tailings Drying Cells
Client: Pembroke Olive Downs Pty Ltd
Pentacon is the principal contractor & scope of work is to construct the storage facilities and drying cells for storage and disposal of CHPP fine reject at Pembroke Olive Downs Complex.
Project Scope of Works
Site management, environmental and erosion management, safety and quality management, traffic management.
CHPP and associated coal handling infrastructure
Stripping of topsoil
Earthworks cut to fill, cut to stockpile
Excavation and disposal on unsuitable material in and below confined excavations
Trimming and compaction of pavement subgrade
Ground surface treatment under embankment, in cells
Win/import, haul, place and compact embankment
Grass seeding to levee embankment
Gravel wearing course supply and lay
Spillway including rock placement and geofabric
Excavation of perimeter drain
Volumes
Topsoil Strip-87,401m³
Bulk Earthworks-543,548m³
Shotcrete-1,028m