NuGrow Western Downs | Kogan Compost Facility

Client: NuGrow Westerns Downs Pty Ltd

The scope of works was to upgrade the compost and soil manufacturing site in stages as the Principal Contractor for NuGrow Western Downs.

 

Project Scope of Works

  • Implementing environmental control measures

  • Detailed earthworks within the Leachate Pond and seepage detection sump

  • Subgrade preparation including placement and compaction of clay Liner

  • All materials and compaction testing of embankment and dam liner materials

  • Construction of water retaining embankments

  • Installation of leak detection sump and associated HDPE pipe work

  • Installation of underdrainage

  • Installation, welding and certification of HDPE liner

  • Construction of concrete sill and anchor trench

  • Construction of spilly way, rock chutes, and drainage channels

  • Construction of access road unbound pavement and road furniture

  • Landscaping, seeding and rehabilitation of disturbed areas

  • Provision of Quality Assurance Package at completion of the works

  • Trim Compost stockpile pad.

  • Install Upstream bunding and drainage to allow Leachate to flow as intended