Alpha HPA is developing a High Purity Alumina (HPA) project to support the growing demand in the electric vehicle and battery production markets. The large-scale commercial plant has been constructed in Yarwun, Qld, Australia.

 

Project Scope of Works

  • Establishment of Site Access and Site Facilities

  • Removal of existing rubble, buried foundations and Unsuitable Material

  • Clearing and Grubbing and Removal of Topsoil for Reuse on site

  • Establishment and management of a Haul Road for Bulk Earthworks

  • Establishment & Import of Select Fill from the nominated Borrow Location

  • Bulk Earthworks Cut to Fill and Pavement Subgrade Preparation

  • Road Pavement Construction

  • Stormwater Drainage including outlets and Rock Protection

  • Installation of new Sewer Mains including Manholes and Live Connection

  • Construction of HDPE Trade Waste and Process Water Ponds

  • Construction of Permanent Stormwater Detention Basin

  • Landscaping, Respreading Topsoil Turfing and Seeding

  • Construction of Concrete Sleeper and Sandstone Boulder Retaining Walls

  • Collation of Quality Assurance Package and As Constructed Data

Special Features

  • 20,000m3 cut to fill site won materials

  • 75,000m3 of imported of Select Fill from the nominated Borrow Location

  • External stormwater remediations to ensure positive downstream drainage.

  • 250m of sleeper and post retaining wall with innovative outlets for storm water drainage outlets