Mackay Regional Council | Forbes Road Causeway Replacement

Client: Mackay Regional Council

Mackay Regional Council | Forbes Road Causeway Replacement

 

The scope of works was to replace the existing causeway and fishway at O’Connell River on Forbes Road, Bloomsbury. Pentacon installed a new higher-level causeway including a new fishway.

 

Project Scope of Works

  • Establishment of Site Access, Site Facilities and Traffic Management Controls

  • Survey set out;

  • Location and protection of existing services;

  • Provision for traffic and liaison with residents;

  • Quality control and compliance testing of the Works;

  • Clearing and grubbing works;

  • Implementation of ESCP and dewatering & temporary diversion bypass

  • Bulk Earthworks;

  • Subsoil and pavement drainage Works;

  • Structural concrete works;

  • Revegetation works/ hydro-mulching of disturbed areas;

  • Supply and installation of road furniture/signage;

  • Construction of stormwater structures and protective treatments;

  • Construction of fishway;

  • Construction of bitumen/aggregate pavement-sealing works;

  • Restoration of all disturbed areas

Special Features

  • The O’Connell River is a permanently flowing river. Dewatering / diversion / staging of the construction was required to accommodate flows.

  • The construction of the fishway was overseen by a suitably qualified third-party person, with reports prepared for submission to the Department of Agriculture and Fisheries (DEF), as per condition 10 of the SARA decision notice.

  • Cultural heritage monitoring required and was completed by YUWI